Permit coordination underway · What to know
The county is waiting on the Pirate Harbor permit before combining the projects.
An Oct. 15 update on Charlotte County's Alligator Creek project page says the Army Corps of Engineers approved permit recertification.
The county says it is awaiting a permit for Pirate Harbor so the two dredging projects can be combined for cost efficiency.
The project schedule lists an estimated construction start of July 3, 2027, and forecast completion of Dec. 3, 2027.
Keep the original source handy
Schedules and details can change. Check the linked source for updates before making plans.
Behind this brief
Source: Charlotte County public project status. This is an attributed summary of the linked public information.
Read the original sourceKeep reading
Charlotte County offices will close Nov. 26–27
Charlotte County lists holiday office closures Thursday and Friday, Nov. 26–27. Plan county-office visits around those dates and confirm individual service schedules.
Charlotte commissioners accept impact-fee study without implementing new rates
Charlotte County commissioners unanimously accepted an updated impact-fee study Nov. 10 without putting its fee schedule into effect.
Charlotte County resident survey closes Dec. 3
Charlotte County residents can give feedback on quality of life and county services through an online survey closing Dec. 3.